18.06.2020 Deutsche Windtechnik completes first job for AES on Siemens 2.3 in Merkel, Texas

In April 2020 a team of five service technicians completed two main component exchanges for AES on Buffalo Gap 3 in Merkel, Texas. The scope of work included two gearbox exchanges where one of the gearboxes was stuck on the main bearing causing a slight delay in the job completion.

Another unexpected element was the outbreak of Covid-19 enforcing Texas State recommendations to implement strict safety measures and adapt site management to be able to complete the job safely and unaffected.

Deutsche Windtechnik received a NPS score of 9/10 confirming a job well done: “The crew lead was proactive in safety”, confirms Justin Calcote, AES-Site Manager at Buffalo Gap 3.

Get in touch with George Ward (g.ward@deutsche-windtechnik.com) for more information on how Deutsche Windtechnik can support your wind farm needs in the US.